Construction Progress

PHASE 1:

Classroom Building, Assembly Hall, 4 Faculty Duplex Bungalows, Site Work, Utilities, Water Distribution, Project Management, Furniture

 

Budget: $735,780 -
Actual Project Total: $654,756
Completed February 2008

PHASE 2:

Girls Dormitory, Kitchen, a Road, Streetlights, Project Management, Furniture 

Budget: $495,000 -
Actual Project Total: $459,883 

Completed September 2008

PHASE 3:  

Boy’s Dormitory 

Budget: $286,121 -
Actual Project Total: $258,743 
Completed October 2010